/ Plan review · Educational library

Most comments are a missing drawing, not a mysterious code.

These are patterns from Daily Code Talk and live Miami-Dade / Florida review — not a script, and not a claim that your letter contains them. Use the classifier if you already have a letter. Send the letter if the decision is live.

Open the comment classifier Permit comment response service

Typical askWhat the set is usually missingStart here
Provide attic / crawl ventilation calculationNAT openings or 0.02 cfm/ft² + supply + RH > 60%IMC 406
Identify damper type at each rated crossingAssembly first — not “F/S where required”IMC 607
Provide makeup / transfer for exhaust-only rooms501.4 path drawn — not door undercuts for large offsetsTransfer air
Ignition source elevation / garage vestibule18 in or FVIR; vestibule where a fuel-fired room opens to a parking garageIMC 304
Provide outdoor-air calculations per occupancyOccupancy, area, people, method, and Vbz on an M-sheet — “OA per code” is not a calculationVentilation · Estimator
Dimension grease exhaust termination40 in above roof, wall path limits, 10 ft / 3 ft to OA intakes — not “per 506”Termination · Tool
Natural vs mechanical outdoor airIMC 401 vs 403 method stated; operable sash is not Table 403401 vs 403
Change of occupancy / heavier useNew method for OA, exhaust, plumbing, grease — existing RTU is not proofChange of occupancy
Identify hood type / grease duct / makeup airEquipment schedule, Type I vs II, 506 construction, 508 replacement air, suppression interfaceKitchen hub
Show fire/smoke dampers at rated assembliesEach crossing: assembly, damper type, listing, access. Not a typical that says “where required”Ducts · Pathfinder
Garage ventilation method and CO controlContinuous vs automatic, Full-On 0.75 / Standby 0.05, detector listing, accessory-room pressureGarage · 404 tool
Combustion air for fuel-fired appliancesMethod, net free area, damper interlock, existing-closet volumeCombustion air
Load calculations / energy formsIMC 312 + Florida envelope/energy path actually usedLoads
Equipment access / condensate / locationIMC 303–307 on the plan, not only in the spec. 30×30 drawn. Overflow path if the primary drain stops.Access · Condensate
Plumbing isometric / fixture units / greaseWaste/vent isometrics, interceptor sizing basis, Miami-Dade plumbing checklistPlumbing
Panel schedules / working clearance / AICNEC 110.26, existing gear photos, available fault current pathElectrical
Existing vs new vs demo not identifiedExisting-building sets that look like new constructionExisting buildings

This library is educational. It is not a representation that any comment will be approved, withdrawn, or accepted on resubmittal. The AHJ decides. Masterbuild’s job is a written, citable drawing response under a written scope.

What to send

The comment letter (PDF), a share link to the current set, the permit number, the jurisdiction, and which comments you want Masterbuild to own. Do not paraphrase the letter.

Send the letter, not a summary of the letter

Permit number, jurisdiction, current set, and the comments you want owned. Written path after scope review.