/ Field knowledge · IMC 306

The 30×30 has to be drawn, not hoped for.

IMC 306.1: you service the appliance without tearing out permanent construction, rated assemblies, or unrelated systems. A 30 in × 30 in level working space at the control/service side is the inspection gate — draw it.

Educational 2024 IMC 306. Confirm the adopted edition and the listing. This is not a clearance design for your unit.

What reviewers actually look for

Lost to later coordination

Structure, ducts, piping, and electrical get placed after the unit footprint. The 30×30 disappears. Draw the box on M-101 before those trades fill it.

Source: DCT 306 Part 1 · roof: 306.5 · tool: access check.

What to send

Equipment location (room / attic / roof / above ceiling), architectural plans, and photos of the space as it sits today on a replacement.

If a tech cannot reach the unit without demolition

Send the location and the photos. Masterbuild will say whether 306 is a drawing dimension or a layout fight.