Outdoor air is a drawing problem, not a note that says “per code.”

IMC Chapter 4 decides whether a space gets outdoor air by occupancy table, by exhaust, or by a healthcare standard. Masterbuild puts the method, the numbers, and the intake locations on the M-sheets so plan review is not guessing.

What the drawings should identify

Where Miami sets lose weeks

Table 403 used as a slogan

A schedule that says “OA per code” without occupancy, area, and people is not a calculation. Reviewers ask for the math because the math is the code path.

Intakes that clear the wall but not the grease exhaust

Kitchen and garage terminations eat outdoor-air intake locations. See the kitchen hub and garage ventilation hub.

Healthcare treated as an office

Ambulatory care and I-2 are not Table 403 rooms with nicer finishes. They are an ASHRAE 170 problem. See healthcare ventilation.

Educational outdoor-air estimator

Run occupancy, area, and optional headcount against IMC Table 403.3.1.1 educational rates. It returns breathing-zone outdoor air (Vbz), not a sealed design.

Open the outdoor-air estimator

Daily Code Talk on this hub

Is Table 403.3.1.1 enough to size outdoor air for a Miami TI?

It is the starting math for many occupancies, not the whole design. System outdoor air can increase after zone air-distribution effectiveness, multiple-zone correction, exhaust makeup, and local amendments. Healthcare follows ASHRAE 170 / IMC 407.

What to send

Architectural plans with occupancies and areas; existing HVAC information; exhaust that must be made up; permit comments if any. Restaurants: add the equipment schedule.

Send the occupancy plan

Areas, occupancies, and whatever HVAC already exists. Masterbuild will say whether this is Table 403, an exhaust-makeup problem, or a 170 path.

Send Project Background

+1 (786) 398-6940  ·  osmany.portal@masterbuildconsulting.com

Masterbuild provides engineering services under a written scope. Nothing on this page is project-specific engineering advice, a code interpretation for your project, or a representation about permit approval.