/ Field knowledge · IMC 607

Name the assembly. Then pick the damper.

IMC 607: the first question is not “where is the fire damper?” It is “what assembly is being penetrated?” Fire walls, fire barriers, fire partitions, smoke barriers, smoke partitions, shafts, corridors, and rated ceiling membranes do not all take the same device.

Educational 2024 IMC 607 from Daily Code Talk. Confirm adopted edition, IBC assembly type, listing, and manufacturer instructions. This is not a damper schedule for your job.

“F/S where required”

A generic symbol hides the wrong device until submittal or inspection. Dryer ducts: no fire damper (see IMC 504).

Source: DCT 607 Part 1 · tool: damper pathfinder · access: 607.4 · walls: 607.5.1–607.5.2 · partitions: 607.5.3 · corridors: 607.5.4 · shafts: 607.5.5 · floors: 607.6 · ducts: Chapter 6.

What to send

Life-safety / rated plan, RCP or duct plan, and any existing damper schedule. Photos of ceiling access on a retrofit.

If the typical says “F/S where required”

Send the rated plan and the duct routing. Masterbuild will say whether this is a damper type question or a missing overlay.