/ Field knowledge · IMC 109

The utility’s meter-set is not the AHJ’s yes.

IMC 109: the utility’s meter-set is not the AHJ’s authorization. No one may connect gas, power, water, or other utilities to IMC-regulated systems until the code official authorizes it.

Educational 2024 IMC 109. Confirm adopted edition. This is not a utility release. Distinct from IMC 110 temporary equipment. Packet: 109 PDF · ES.

Utility release ≠ AHJ authorization

They are separate requirements. Bypass LOTO for partial energization during commissioning and you have created the next incident. In renovations, the most common error is assuming the existing connection covers the new piece of equipment.

Source: DCT 109 · tool: energize screen · temporary: 110 · inspections: 111.

What to send

Whether you have written AHJ authorization, a utility release, or neither — and which utility is about to be connected.

If the GC wants to energize tomorrow

Send what writing you have. MasterBuild will say whether 109 even has an authorization — or this is already a disconnect conversation.

Send Project Background

+1 (786) 398-6940 · osmany.portal@masterbuildconsulting.com