/ Miami-Dade · Temporary power
Temporary power is not FPL dropping the service for a repair.
Temporary power is a permitted system with a duration and a removal plan. It is not FPL dropping the service for a repair. Original Masterbuild writing — not a copy of the County electrical-inspection.pdf. Daily Code Talk on IMC 110: do not assume a universal 180-day limit for temporary systems. We do not invent Article 110 numbers. We do not quote temp-power dollars.
Packet: temp power PDF · ES. Work-with: FPL drop-and-pick-up. Fees: which application. IMC 110: temporary uses.
- Work-with — existing service, FPL drops and picks up while you repair. Thirty-day clock. Access every panel.
- Temporary power / construction service — a system that is not the permanent service. Name duration, load, grounding, who removes it.
- A generator for construction is still listed equipment with grounding and exhaust. It is not “plug into the house.”
- HB 803 did not exempt mechanical, and it did not exempt temporary electrical just because it is temporary.
Called as a work-with, actually a new temp pole
FPL will not pick up what was never dropped. Two clocks, one wasted truck.
What to send
Whether this is construction power, a generator, or a work-with on an existing service, plus duration and who removes it.
If the pole is already in the dirt and nobody named a duration
Send the photo. Masterbuild will say whether temp power still has no row — not whether the inspector will pass.