Gas piping still has to be bonded.
Gas piping still has to be bonded. “Electrical will catch it” is not a bond. Original Masterbuild writing — not a copy of the County plumbing-inspection.pdf. County plumbing and gas finals look for bonding of gas piping when there is no electrical permit covering that bond. We do not invent a bonding-jumper size.
Packet: gas bond PDF · ES. Plumbing inspection-day: dry pan is a story. Electrode: before the pour.
- A gas-only permit still leaves a bonding row. Water-heater swap, range, dryer, pool heater — if electrical was never permitted, plumbing/gas is looking at the bond.
- Metallic water service used as the grounding electrode is a different, related fight. Do not swap it to plastic until another approved electrode is in place.
- Pressure test is not the bond. Flue slope is not the bond. LP tank distances are NFPA 58 — we do not publish a number here.
Gas final called, bond missing, metallic water already plastic, electrical never permitted
Two trades, one missed jumper. Re-inspection.
What to send
Whether there is an electrical permit on this job, a photo of the gas piping bond (or the lack of one), and whether metallic water service was replaced.
If the gas final is tomorrow and electrical was never pulled
Send the photo. Masterbuild will say whether the bond still has no row — not whether the inspector will pass.