Daily Code Talk #178IMC 910.1–910.3 Floor Furnaces: Placement, Thermostat and Framing (1/2)

Floor furnace placement affects circulation, nearby combustibles, thermostat sensing and framing.

By Osmany Portal, PE

Permit Proof Chain

01Code TriggerIdentify why the section applies.
02Sheet EvidenceShow the requirement where the reviewer needs it.
03Coordination OwnerTie the requirement to the responsible discipline or party.
04Field ProofConfirm the installed condition can be verified.

910.1 Listing and instructions

Install the selected floor furnace in accordance with its listing and manufacturer instructions. For an oil-fired floor furnace, verify testing to UL 729. Put the model in the equipment schedule so the proposed opening and installation can be checked against actual product data.

910.2 Placement

Do not place a floor furnace in the aisles or passageways of auditoriums, public halls, places of assembly, or an egress element serving those spaces. Except for wall-register models, keep the unit at least 6 inches from the nearest wall. A wall-register model stays at least 6 inches from a corner; draperies or similar combustibles stay at least 12 inches from any portion of the register. Show these dimensions on the architectural plan.

A floor furnace is not permitted in concrete floor construction built on grade. Locate its controlling thermostat in the same room or space, or in an adjacent room or space permanently open to it.

910.3 Framing

The floor around the furnace opening needs bracing and a supporting framework designed under the International Building Code. Coordinate the framed opening before the mechanical location is fixed.

What changes in the field

A unit can fit in plan and still conflict with the egress route, furnishings, thermostat sensing or structural framing. Review the mechanical plan, architectural circulation and structural framing together before permit.

Field check

Compare the proposed opening with prohibited egress locations and slab-on-grade construction.

Dimension wall, corner and combustible furnishing separation.

Show the thermostat's relationship to the served room and the structural opening.

Where to show it

Mechanical and architectural plans

Thermostat plan

Structural framing detail

Code basis

2024 IMC Sections 910.1–910.3 model-code education. Confirm the locally adopted edition and amendments, the selected product listing and manufacturer instructions, and the authority having jurisdiction. Read the ICC 2024 IMC Chapter 9 for the complete model-code provisions.

PE-led project support

Need this applied to a live project?

MasterBuild Consulting helps owners, architects, GCs, and project teams turn code questions into permit-ready MEP decisions before review comments, field changes, or inspection issues cost more time.

Daily Code Talk uses the 2024 IMC as model-code education. Verify adopted code, listings, manufacturer instructions, and AHJ path before project use.

Related Daily Code Talk posts